Peace River Cumulative Impact Assessment

Timeline

Major project tasks of the Peace River Cumulative Impact Study along with a preliminary schedule is shown below. The schedule will be periodically updated as progress is made.

Task 1 - Literature Review, Data Collection and Detailed Scope of Work

Task 1 is expected to last from 3 to 6 months.

Task 2 - Description of Historical Changes

Task 2 is expected to last from 3 to 6 months depending on data assimilation. This phase may proceed concurrently with the latter stages of Task 1.

Task 3 - Identification and Analysis of Factors Causing Changes

Task 3 is expected to last from 3 to 6 months. This phase may proceed concurrently with the latter stages of Task 2.

Task 4 - Evaluate Regulatory Effectiveness

Task 4 is expected to last from 1 to 3 months. This phase may proceed concurrently with the latter stages of Task 2.

Task 5 - Technical Report

Task 5 is expected to last up to 3 months.

Task 6 - Meetings

Task 6 is expected to occur periodically throughout the project duration (12 months).